Kenai Peninsula Borough in southern Alaska needed to complete phase two of a landfill-closure project at its Homer Solid Waste Facility. This involved the closure of about 226,000 ft² (21,000 m²) of landfill using a geosynthetic clay liner and installing a drainage and landfill-gas system. Qayaq Construction, the contractor, selected Solmax to supply its geosynthetics solutions due to its ability to meet the highly challenging conditions at the site.
Homer’s sub-arctic coastal climate can be unpredictable, leaving tight windows for deployment. In addition, a road to the east of the landfill-closure operation was to be utilized for public access for much of the work. Coordination between normal landfill operations and the closure also had to be considered.
In terms of physical site challenges, the landfill closure involved extremely steep gradients and poor sub-surface conditions. Differential settlement was also a concern.
Solmax’s solution provided Qayaq Construction with the flexibility it needed to get the job done, by allowing for rapid deployment with minimal impact on daily landfill operations.
With geosynthetic designs, including GCLs and drainage nets, proving successful for previous phases of the Homer landfill closure, the Solmax solutions selected by Qayaq were 231,000 ft² (21,450 m²) of BENTOLINER® NWL-35; a similar amount of 250mil (6.35mm) FABRINET® geocomposite, and 47,360 ft² (4,400 m²) of 40mil (1mm) double-textured GSE® LL geomembrane.
BENTOLINER is a versatile, fabric-encased GCL. It is intended for moderate-to-steep slopes and moderate-to-high load applications where increased internal-shear strength is required. Our FABRINET geocomposite met the necessary criteria for drainage, filtration, and puncture protection. The GSE LL added frictional resistance, having been designed for applications that require increased elasticity and multi-axial break resistance where differential or localized settlements may occur, such as in landfill closures.
To ensure full conformity and add further security, Solmax provided additional third-party testing of its shear and permeability results. The result is a landfill-capping system that meets the needs of this unique location and environment, as well as those of the client.
Solmax geosynthetics, including BENTOLINER, FABRINET geocomposite, and GSE LL geomembrane, were utilized to manage the steep gradients and poor sub-surface conditions of the site
The Homer Solid Waste Facility's landfill closure covered 226,000 ft² using a geosynthetic clay liner and included the installation of a drainage and landfill-gas system
Flood protection for Reinland Drain in Manitoba
PROPEX® Armormax® stabilized the eroded Reinland Drain, reducing costs and emissions while ensuring long-term flood protection with reinforced vegetation growth.
Comprehensive containment and capping at Thailand’s ESBEC landfill
Solmax supplied GSE® HD liners and BENTOLINER® GCLs to line and cap Thailand’s ESBEC landfill, ensuring full containment, leachate and gas control, and compliance with national and international waste standards.
Providing a stabilized platform for site development in soft soil and flood-prone areas: an alternative to traditional stabilization methods
MIRAFI® RS580i stabilized parking areas at Knapheide’s Moncks Corner facility over soft, floodplain-adjacent soils, enabling rapid construction, eliminating chemical treatment, reducing material haulage, and delivering durable performance under heavy vehicle loading.