Subgrade stabilization for stormwater management
Overview
Climate change and poor water resource management, such as river channel and floodplain mismanagement, have increased flooding and erosion problems. Insufficient drainage and sewerage capacity in urban areas exacerbates the risk of flooding. To address these issues, detention and retention systems are commonly employed in urban planning and development to prevent flooding.
Challenge
This project is located at Taman SPPK, Segambut in Malaysia. Due to inadequate drainage, the area faces a high flood risk during intense thunderstorms. To mitigate this, an underground stormwater detention system called StormTrap® Double Trap was implemented. This system stores water runoff in an underground chamber before releasing it back into the drain. StormTrap is a leading provider of stormwater management systems that offer cost-effective solutions for engineers, owners, and municipalities. The land above the underground system will be utilized for playgrounds and parking lots. However, the construction was hindered by soft subgrade soil.
The project area had a soft soil depth of 7.0m (22.97 ft), with the groundwater table nearly at the same level. The soft soil consisted of 3.0m (9.84 ft) of marine soft clay at the top and 4.0m (13.12 ft) of very soft sandy silt at the bottom before reaching firm ground. To address the issue of the soft subgrade, a stable load transferring platform was required to support the underground stormwater detention system.
Solution
The construction process began with the installation of sheet piles around the entire project perimeter, followed by excavation to the designed depth for the load transferring platform. Bakau piles were installed with a spacing of 500mm (19.69 in). A thin layer of soil was then backfilled to create a flat surface for laying the geotextile. MIRAFI® HP380a geotextile was placed over the entire platform area. Finally, a 500mm (19.69 in) thick layer of compacted aggregate fill was added on top of the MIRAFI HP380a geotextile to complete the construction of the stabilized load transferring platform. The subsequent construction involved installing the StormTrap system and backfilling the soil on top.
Result
Geosynthetics, such as MIRAFI HP380a geotextile, have proven to be effective in enhancing the performance of roads and load support structures. The MIRAFI HP380a geotextile provides functions of separation, reinforcement, lateral confinement, and permeability, which help stabilize the soft subgrade and transfer the load from the stormwater detention system to the piles.
Taman SPPK, Segambut, Malaysia Stormwater development MIRAFI HPa
Taman SPPK, Segambut, Malaysia Stormwater development MIRAFI HPa
Taman SPPK, Segambut, Malaysia Stormwater development MIRAFI HPa
More case studies
View all
Providing long term stabilization for drainage channel
PROPEX Armormax and PROPEX Pyramattress, an engineered mattress system that uses PROPEX Pyramat 75 HPTRM to construct a geosynthetic/soil/rock composite for protection of channels, slopes, and spillways.

Steep slope stabilization at SR-11 KYTC DISTRICT 10
The PROPEX Armormax system helped KYTC meet their goal of providing a safe, efficient, environmentally sound and fiscally responsible option to repair the slope while also ensuring access to the state park and economic growth in the surrounding area.

Providing levee resilience and durability
Full scale installation of the EEAS began in 2015 and has since been installed on over 100 miles of earthen levees in the New Orleans area. Since installation, multiple levees have experienced overtopping from major hurricanes, but have not breeched.