Overview
The Jamnagar refinery, located in northwest India, is a crude oil refinery with a production capacity of 661,000 barrels per day. To accommodate the planned expansion of doubling its production capacity to 1.2 million barrels per day, a significant amount of wastewater will be generated during the crude oil extraction process. To prevent environmental contamination, it was decided to dispose of the treated wastewater through pipelines laid on the seafloor. The project involved laying five 1.4m (4.6 ft) diameter pipes over a distance of two and a half kilometers (1.6 miles) in a pre-dredged trench measuring 70.5m (231.3 ft) wide and 3.5m (11.5 ft) deep.
Solution
To ensure separation between the bedding material and the silt, a layer of MIRAFI® Polyfelt® TS009 nonwoven geotextile was placed at the bottom of the trench. This was followed by a 300mm (11.8 in) thick layer of well-graded aggregates. The MIRAFI Polyfelt TS009 geotextile acted as a separator, preventing the loss of aggregate into the soft subgrade of the seafloor and maintaining the structural integrity of the aggregate fill layer. After the pipes were installed, the trench was backfilled with in-situ soils. The decision to lay the pipelines in a trench was made to protect them from potential damage caused by local navigation.
On-site, two sections of MIRAFI Polyfelt geotextiles measuring 4 m (13.1 ft) in width were stitched together longitudinally, forming 7.5 m (24.6 ft) wide geotextile panels. These panels were then accurately deployed at the base of the trench using an 8 m (26.2 ft) wide spreader bar mounted on a crane situated on a floating barge. The 7.5 m (24.6 ft) wide x 2.5 km (1.6 miles) long MIRAFI Polyfelt TS009 geotextile was rolled off into the water with the assistance of counterweights in the form of bags filled with aggregate. Divers were employed to facilitate the installation of the MIRAFI Polyfelt TS009 geotextile. The pipes were placed at a distance of 3.5 m (11.5 ft) center to center within the trench. This careful selection of construction materials and their installation proved to be a significant cost-saving measure.
Jamnagar Refinery Pipelines, India Waste management MIRAFI Polyfelt TS
Jamnagar Refinery Pipelines, India Waste management MIRAFI Polyfelt TS
Jamnagar Refinery Pipelines, India Waste management MIRAFI Polyfelt TS
Jamnagar Refinery Pipelines, India Waste management MIRAFI Polyfelt TS
More case studies
View all
Providing long term stabilization for drainage channel
PROPEX Armormax and PROPEX Pyramattress, an engineered mattress system that uses PROPEX Pyramat 75 HPTRM to construct a geosynthetic/soil/rock composite for protection of channels, slopes, and spillways.

Steep slope stabilization at SR-11 KYTC DISTRICT 10
The PROPEX Armormax system helped KYTC meet their goal of providing a safe, efficient, environmentally sound and fiscally responsible option to repair the slope while also ensuring access to the state park and economic growth in the surrounding area.

Providing levee resilience and durability
Full scale installation of the EEAS began in 2015 and has since been installed on over 100 miles of earthen levees in the New Orleans area. Since installation, multiple levees have experienced overtopping from major hurricanes, but have not breeched.