Stabilizing soft agricultural land for heavy crane loads
Solmax supplied 32,500 m² of MIRAFI HMi to stabilize soft agricultural land for crane use, completing winter installation on schedule in four weeks.
The Old Pacific Highway is the original freeway section which runs parallel to the current Interstate 5. Nestled on the hillside, a global stability issue created a slide of the natural slope and a large crack in the pavement section.
This project was treated like a deep patch repair and initial repair strategies conceptually included the removal and disposal of the existing asphalt roadway and aggregate subbase, over-excavation of native subsurface soils to a depth anticipated between 2 and 6 ft, the installation of four layers of geogrid in combination with Crushed Surfacing Base Course (CSBC), and Hot Mix Asphalt (HMA) surfacing. However, during geotechnical exploration, an area of high saturation was noted at the bottom of the slip zone, approximately 6 ft down from the existing road surface. The project team was worried that if they repaired this section without addressing the moisture issue, it would not be long until the same section of roadway required additional repair.
The MIRAFI® H2Ri system was selected because it provides a long-term defense against saturated soils under the steepened slope. The main goal was to prevent accumulation of moisture below the slope repair, where there is a known slip plane which has been problematic. The project team acknowledged that the saturated zone would be a continuing problem. The MIRAGRID® Miramesh facing met aesthetic requirements and long-term performance. The revised solution did not deviate much from the anticipated repair plan and allowed the project team to move forward without over excavation and increased reinforcement lengths.
The MIRAFI H2Ri system was installed to prevent moisture accumulation beneath the slope repair, addressing the known slip plane and ensuring long-term stability
Four layers of geogrid were combined with CSBC and HMA surfacing, reinforcing the roadway while mitigating soil saturation at the bottom of the slip zone
The revised repair plan incorporated the MIRAGRID Miramesh facing to meet aesthetic and performance requirements, allowing the project team to proceed without over-excavation or extended reinforcement lengths
Stabilizing soft agricultural land for heavy crane loads
Solmax supplied 32,500 m² of MIRAFI HMi to stabilize soft agricultural land for crane use, completing winter installation on schedule in four weeks.
Resilient rural road construction in Thailand using MIRAFI H2Rx geotextile
A rural road in Thailand was upgraded using MIRAFI H2Rx geotextile to reinforce soft clay subgrade and manage high groundwater, ensuring durability, reduced moisture, and uninterrupted community access during construction.
Strengthening canal-adjacent road infrastructure in Thailand with MIRAFI H2Rx
MIRAFI H2Rx geotextile was installed over 27,000 m² to reinforce a road near Maharahj canal, improving pavement strength and moisture control while preventing embankment failure and completing 3 km in just 5 days.