The Davao City coastal road bypass project aims to alleviate traffic congestion in the city by constructing a road from Roxas Avenue to Bago Aplaya, passing through NHA Kadayawan Homes, Matina Aplaya, and Bolton Isla. Three roundabouts will be installed along the 35 km (21.7 mile) coastal stretch at Roxas Avenue, Times Beach area, and Matina Aplaya.
Due to the region's growing population and ongoing development, traffic congestion on major roads has become a significant problem. The coastal road project aimed to address this issue.
In the Bago-Aplaya Section facing Davao Gulf towards Talomo, an elevated highway with a 90-degree vertical slope on both sides, the contractor needed to stabilize and reinforce the embankments effectively.
For this project, a segmental block wall reinforced with MIRAGRID® GX geogrid was chosen. This design offers fast, durable construction. MIRAGRID GX geogrid possesses the necessary properties for long-term reinforcement, including high tensile strength at low elongation, minimal creep, and low installation damage. Its superior interlocking mechanism and connection capacity to block wall systems make it an ideal choice.
Construction:
The reinforced segmental block wall system involved the use of precast concrete blocks arranged to form the wall facing. The soil/sand backfill behind the wall was reinforced with MIRAGRID GX geogrid. The blocks were designed with an interlocking mechanism that securely connected them. The geogrid reinforcement was placed horizontally on the soil backfill and connected to the concrete blocks at specific design heights of the wall.
Performance:
By utilizing MIRAGRID GX, the construction of the reinforced segmental block wall system resulted in a relatively flexible structure capable of accommodating differential settlement without causing damage. The project successfully achieved the goals of stabilization and reinforcement, while also being completed within the designated time and cost parameters.

DAVAO CITY COASTAL ROAD, PHILIPPINES

Rebuilding resilience: post-wildfire erosion control on Pacific Palisades bluff
A homeowner used PROPEX Armormax to protect a bluff damaged by the Pacific Palisades fire to reduce erosion risk, support revegetation and mitigate future wildfires.
Seawall construction, Brisbane Port expansion, QLD, Australia
The Port of Brisbane expanded by constructing a reinforced seawall to enable 230 ha of land reclamation using dredged materials while managing soft clay foundations and protecting the Moreton Bay Marine Park.
Restoring marine health in the Marmara Sea with GEOTUBE dewatering
Kocaeli Municipality and Türkiye Ministry deployed 3,500 GEOTUBE units to dewater contaminated sludge from Kocaeli Bay, targeting 60% dry solids and supporting Marmara Sea restoration.