Continuous rainfall caused a major landslide on the Federal Route leading to Langkawi's highest mountain (881m/2,890 ft). This area houses a museum, a park, and a satellite control centre. The landslide severely disrupted traffic and posed risks to road users.
The high, steep, and unstable failed slope made it difficult to trim it into a gentler gradient using conventional methods. After considering various solutions, PWD engineers decided to realign the road, moving it 30m (98 ft) away from the failed slope. This required constructing a geosynthetics reinforced slope starting from the toe of the failed area below the road.
Since there was no granular material available at the site, the design focused on using the fine sandy soil already present as backfill. MIRAFI® Polyfelt PEC reinforcement geotextile was chosen due to its high tensile strength, optimal reinforcement/soil friction interface, and effective in-plane drainage in such soils.
The reinforced soil structure consisted of a 30m-high (98 ft) slope reinforced from the toe of the failed embankment. The facing system used involved wrapping a net around bags filled with fine-grained soil. This construction method allowed for the practical creation of a curved slope. MIRAFI Polyfelt PEC was placed behind the gabion and soil bags to enhance the structure's strength. Additionally, a layer of MIRAFI Polyfelt PEC TS geotextile filter was installed behind the gabions to prevent soil piping through the voids.
The primary reinforcement direction of MIRAFI Polyfelt PEC was perpendicular to the slope's surface. The reinforcement geotextile was pretensioned and secured with wooden pegs. Backfill material was compacted using a 10-ton compactor to achieve a minimum of 90% proctor compaction. Finally, hydroseeding was performed to establish vegetation on the completed slope.

Slope failure repair using MIRAFI Polyfelt PEC: Langkawi, Malaysia

Slope failure repair using MIRAFI Polyfelt PEC: Langkawi, Malaysia
Flood protection for Reinland Drain in Manitoba
PROPEX® Armormax® stabilized the eroded Reinland Drain, reducing costs and emissions while ensuring long-term flood protection with reinforced vegetation growth.
Comprehensive containment and capping at Thailand’s ESBEC landfill
Solmax supplied GSE® HD liners and BENTOLINER® GCLs to line and cap Thailand’s ESBEC landfill, ensuring full containment, leachate and gas control, and compliance with national and international waste standards.
Providing a stabilized platform for site development in soft soil and flood-prone areas: an alternative to traditional stabilization methods
MIRAFI® RS580i stabilized parking areas at Knapheide’s Moncks Corner facility over soft, floodplain-adjacent soils, enabling rapid construction, eliminating chemical treatment, reducing material haulage, and delivering durable performance under heavy vehicle loading.