Lining a tailings facility on the roof of the world
Overview
Solmax geomembranes were used to line the tailings facilities of the recently expanded Yulong Copper Mine. The mine located in the Qinghai-Tibet Plateau, on one of the largest copper deposits in China, is important to the economy of the region.
The Challenge
The mine is located in some of the highest elevations in the world. The Qinghai-Tibet Plateau has an average altitude of 4,700 m (15,400 ft). The area experiences extreme weather conditions where rain and snowstorms continue for days on end and the UV radiation intensity is high all year round. The extreme conditions make construction difficult and pose challenges to organizing labor resources.
The project needed to recruit technical and labor personnel from Sichuan and Tibet through multiple channels. Bulk material procurement was organized in Chengdu and Xining. The project had high requirements for the on-site living quarters of production service providers and construction personnel. It was also important to find logistics providers with sufficient experience in working in remote and harsh environments ensure timely and sufficient supply of construction materials.
Solution
Due to the harsh environment placing restraints on construction, the timelines for this project were tight. The mining waste containment project was an important construction link. The project required a large quantity of high-quality HDPE geomembrane materials. These materials needed to be durable and able to be safely installed. Because the project was a key construction project of the region, it was important to select a geomembrane manufacturer with a global well-known brand, good business reputation and sufficient production capacity.
In 2019, Solmax was selected to supply impervious geomembrane for the project because of its excellent and stable performance and good brand reputation. Solmax has supplied more than 270,000 m² (2.9 million ft²) for this project, including more than 180,000 m² (1.9 million ft²) of 1.5 mm smooth HDPE geomembrane and more than 90,000 m² (970,000 ft²) of 1.5 mm single-side GSE® HD geomembrane for lining the waste dump, intercepting reservoir, retaining dam and reservoir area anti-seepage system.

Lining a tailings facility on the roof of the world

Lining a tailings facility on the roof of the world
More case studies
View all
Providing long term stabilization for drainage channel
PROPEX Armormax and PROPEX Pyramattress, an engineered mattress system that uses PROPEX Pyramat 75 HPTRM to construct a geosynthetic/soil/rock composite for protection of channels, slopes, and spillways.

Steep slope stabilization at SR-11 KYTC DISTRICT 10
The PROPEX Armormax system helped KYTC meet their goal of providing a safe, efficient, environmentally sound and fiscally responsible option to repair the slope while also ensuring access to the state park and economic growth in the surrounding area.

Providing levee resilience and durability
Full scale installation of the EEAS began in 2015 and has since been installed on over 100 miles of earthen levees in the New Orleans area. Since installation, multiple levees have experienced overtopping from major hurricanes, but have not breeched.