
Constructing an artificial island with GEOTUBE
Overview
The Incheon Grand Bridge is a major project that connects Incheon International Airport with Songdo City in the Incheon Free Economic Zone. Instead of using heavy marine equipment to build the bridge piers over open water, an alternative solution was proposed. It involved constructing an artificial island reclaimed from the sea as a temporary platform for the construction process. This option proved to be more cost-effective than alternatives like sheet piles or rock levees.
Challenge
For constructing the edge levees that formed the temporary platform, GEOTUBE® GT1000 was chosen. The GEOTUBE containers used varied in diameter (3 m [9.8 ft], 4 m [13.1 ft], and 5 m [16.4 ft]) and length (15 m [49.2 ft] to 60 m [196.9 ft]). They were stacked in tiers, reaching a height of approximately 7 m [23 ft] above the soft estuarial deposits. The tubes were installed below sea level, about -1.0 m [-3.3 ft] at the shallow end and -2.8 m [-9.2 ft] at the deeper end. In total, over 14 km [8.7 miles] of GEOTUBE engineered tubes were used.
Solution
The tubes were filled with sand, which was delivered by barges to the construction sites. The sand was mixed with seawater to create a slurry and pumped into the GEOTUBE containers. The space within the tubes was then filled with residual soil to complete the platform.
GEOTUBE installation began in April 2006, and at the peak of construction, three installation equipment set-ups were used to fill three tubes simultaneously. By the end of 2006, the full 14 km [8.7 miles] of filled tubes was completed ahead of schedule and within budget.

Incheon Grand Bridge: Constructing Artificial Island

Incheon Grand Bridge: Constructing Artificial Island
Incheon Grand Bridge: Constructing Artificial Island

Incheon Grand Bridge: Constructing Artificial Island
Incheon Grand Bridge: Constructing Artificial Island
More case studies
View all
Providing long term stabilization for drainage channel
PROPEX Armormax and PROPEX Pyramattress, an engineered mattress system that uses PROPEX Pyramat 75 HPTRM to construct a geosynthetic/soil/rock composite for protection of channels, slopes, and spillways.

Steep slope stabilization at SR-11 KYTC DISTRICT 10
The PROPEX Armormax system helped KYTC meet their goal of providing a safe, efficient, environmentally sound and fiscally responsible option to repair the slope while also ensuring access to the state park and economic growth in the surrounding area.

Providing levee resilience and durability
Full scale installation of the EEAS began in 2015 and has since been installed on over 100 miles of earthen levees in the New Orleans area. Since installation, multiple levees have experienced overtopping from major hurricanes, but have not breeched.