Products
Industries
Constructing an artificial island with GEOTUBE
Overview
The Incheon Grand Bridge is a major project that connects Incheon International Airport with Songdo City in the Incheon Free Economic Zone. Instead of using heavy marine equipment to build the bridge piers over open water, an alternative solution was proposed. It involved constructing an artificial island reclaimed from the sea as a temporary platform for the construction process. This option proved to be more cost-effective than alternatives like sheet piles or rock levees.
Challenge
For constructing the edge levees that formed the temporary platform, GEOTUBE® GT1000 was chosen. The GEOTUBE containers used varied in diameter (3 m [9.8 ft], 4 m [13.1 ft], and 5 m [16.4 ft]) and length (15 m [49.2 ft] to 60 m [196.9 ft]). They were stacked in tiers, reaching a height of approximately 7 m [23 ft] above the soft estuarial deposits. The tubes were installed below sea level, about -1.0 m [-3.3 ft] at the shallow end and -2.8 m [-9.2 ft] at the deeper end. In total, over 14 km [8.7 miles] of GEOTUBE engineered tubes were used.
Solution
The tubes were filled with sand, which was delivered by barges to the construction sites. The sand was mixed with seawater to create a slurry and pumped into the GEOTUBE containers. The space within the tubes was then filled with residual soil to complete the platform.
GEOTUBE installation began in April 2006, and at the peak of construction, three installation equipment set-ups were used to fill three tubes simultaneously. By the end of 2006, the full 14 km [8.7 miles] of filled tubes was completed ahead of schedule and within budget.
Incheon Grand Bridge: Constructing Artificial Island
Incheon Grand Bridge: Constructing Artificial Island
Incheon Grand Bridge: Constructing Artificial Island
Incheon Grand Bridge: Constructing Artificial Island
Incheon Grand Bridge: Constructing Artificial Island
Explore more case studies
View allMeeting subgrade stabilization challenges with MIRAFI
Utilizing MIRAFI RS380i geotextile fabric, this project overcame poor subgrade conditions to construct four commercial buildings with stable platforms for parking lots and loading docks.
Biogas cover turns palm oil waste into fuel in Malaysia
Cenergi transforms POME into renewable biogas in Malaysia, using GSE geomembranes. This project reduced GHG and the approach highlights innovation in waste recycling and contribution to renewable energy goals.
IMAX parking lot's innovative stormwater system with MIRAFI
In 2012, Mississauga's IMAX parking lot implemented a low impact development system to manage stormwater, enhancing water quality and maintaining pavement integrity.