In 2020, Xcel Energy faced a fast-approaching deadline to close Sherco Pond No.1, a large coal combustion residuals (CCR) pond in Becker, Minnesota. To maintain continuous service to the energy plant, Xcel Energy had to construct a second pond.
The new Sherco Pond No.2 would need to meet newer, more stringent CCR storage regulations and requirements than its predecessor.
To meet the new regulations and to fulfil the Minnesota Department of Natural Resources requirements, the project required excavation and movement of 458,733 m³ (600,000 yd³) of soil, while also addressing various environmental and wildlife sensitivities.
The challenge was to find a readily available product, that could be installed quickly and meet the performance permeability metric of 1.03 x 10-9 cm/sec. To meet these requirements, the engineers at Carlson McCain chose Solmax to supply geosynthetic clay liners (GCL).
Due to the aggressive nature of the ash leachate, a standard bentonite GCL would not meet the project's permeability requirements. The project required a polymer enhanced product and proof that the GCL would meet the regulatory requirements for permeability.
Dr Craig Benson conducted hydraulic conductivity testing following ASTM D6766 on BENTOLINER® Coal Ash Resistant (CAR) polymer enhanced GCL to test the compatibility with the Xcel Sherco bottom ash leachate. The test results concluded that the hydraulic conductivity of the BENTOLINER CAR was 8.3 x 10-10 cm/sec. The samples had successfully reached hydraulic and chemical equilibrium with the leachate, meeting the new CCR storage regulations.
The testing and proof of performance on the BENTOLINER CAR in the harsh environment played a crucial role in the project's success. The work was completed in time to maintain continuous service with minimal impact on the environment. The latest and most stringent CCR regulations were also met for the new landfill.


Rebuilding resilience: post-wildfire erosion control on Pacific Palisades bluff
A homeowner used PROPEX Armormax to protect a bluff damaged by the Pacific Palisades fire to reduce erosion risk, support revegetation and mitigate future wildfires.
Seawall construction, Brisbane Port expansion, QLD, Australia
The Port of Brisbane expanded by constructing a reinforced seawall to enable 230 ha of land reclamation using dredged materials while managing soft clay foundations and protecting the Moreton Bay Marine Park.
High speed railway embankment over karst foundation, Guizhou Province, China
The Anshun–Liupanshui high-speed railway crosses challenging karst terrain in Guizhou Province. Two layers of MIRAFI PET600 geotextile reinforcement were installed at the embankment base to limit deformation and manage subsidence risk under strict settlement criteria.