Stabilizing soft agricultural land for heavy crane loads
Solmax supplied 32,500 m² of MIRAFI HMi to stabilize soft agricultural land for crane use, completing winter installation on schedule in four weeks.
To rebuild approximately 6 acres of parking lots for a commercial office complex in Maine. The existing parking areas to be rebuilt were in poor condition due to a high moisture content in the subgrade soils and years of frost heaving from extensive freeze thaw conditions during the severe Maine winters. The additional challenge was to minimize the amount of over excavation of the base course which would reduce overall construction time without sacrificing structural stability and to finish construction before the harsh winter weather set in.
After the bores were completed, it was determined that a high-strength structure would need to be added to help support the wheel loads. The design called for the existing asphalt surface to be removed and recycled as well as 6 inch to 8 inch of the compromised structural base course to be removed. The MIRAFI® RS580i was to be placed on top of the remaining base course to add a higher tensile modulus, providing confinement of the base course layer.
Construction began in October and finished in November 2010. The MIRAFI RS580i was installed with a minimum 24 inch overlap between adjacent rolls and a minimum 40 inch overlap at roll ends. Because of its high tensile modulus in the cross-machine direction, the MIRAFI RS580i was rolled out parallel to the travel lanes. The finished base was then proofed rolled and paved.
The MIRAFI RS580i has performed very well by reinforcing and stabilizing the base course, especially during several heavy rain events prior to paving. The MIRAFI RS580i has provided high reinforcement strength, filtration, separation, and base course confinement which has provided better load distribution in the parking areas. The owner’s construction manager and the general contractor were very satisfied with the MIRAFI RS580i which has performed as expected. The project was completed on budget and within the construction time schedule.
The installation process involved removing the asphalt and compromised base, placing MIRAFI RS580i for structural reinforcement, and proof-rolling before final paving.
MIRAFI RS580i was placed on the base course with 24-inch overlaps and 40-inch roll-end overlaps, enhancing confinement and reinforcement for improved load distribution.
The geosynthetic was installed parallel to travel lanes for maximum reinforcement, stabilizing the base course before paving despite heavy rain events.
Stabilizing soft agricultural land for heavy crane loads
Solmax supplied 32,500 m² of MIRAFI HMi to stabilize soft agricultural land for crane use, completing winter installation on schedule in four weeks.
Resilient rural road construction in Thailand using MIRAFI H2Rx geotextile
A rural road in Thailand was upgraded using MIRAFI H2Rx geotextile to reinforce soft clay subgrade and manage high groundwater, ensuring durability, reduced moisture, and uninterrupted community access during construction.
Strengthening canal-adjacent road infrastructure in Thailand with MIRAFI H2Rx
MIRAFI H2Rx geotextile was installed over 27,000 m² to reinforce a road near Maharahj canal, improving pavement strength and moisture control while preventing embankment failure and completing 3 km in just 5 days.