Stabilizing soft agricultural land for heavy crane loads
Solmax supplied 32,500 m² of MIRAFI HMi to stabilize soft agricultural land for crane use, completing winter installation on schedule in four weeks.
The U.S. Army Corps of Engineers (USACE), embarked on one of the largest and most comprehensive public works projects in American history following the catastrophic damage caused by Hurricane Katrina in 2005. The Hurricane and Storm Damage Risk Reduction System (HSDRRS) program was established to provide the greater New Orleans Area a 100-year level of risk reduction. One of the most critical measures of the HSDRRS was protection of refurbished earthen levees against the erosion-causing hydraulic forces of storm surge overtopping. Without protection, overtopping can lead to significant landside erosion and potentially a breach of the levee. During Hurricane Katrina, most levee failure was due to water overtopping.
The USACE needed a proven solution, so they partnered with Colorado State University (CSU) to build a full-scale wave overtopping simulator. The simulator tested erosion resistance of the PROPEX® Armormax® system for 500-year resiliency HSDRRS overtopping conditions. Testing showed that PROPEX Armormax, consisting of High Performance Turf Reinforcement Mat (HPTRM) and Engineered Earth Anchors (EEA), provided increased levee resilience and durability. Additionally testing showed that PROPEX Armormax reinforced vegetation on the earthen levees, which reduces the risk of breaching caused by overtopping waves.
Full scale installation of the EEAS began in 2015 and has since been installed on over 100 miles of earthen levees in the New Orleans area. Since installation, multiple levees have experienced overtopping from major hurricanes, but have not breeched.
Providing levee resilience and durability
Providing levee resilience and durability
Breached Levee
CSU Wave Overtop
Stabilizing soft agricultural land for heavy crane loads
Solmax supplied 32,500 m² of MIRAFI HMi to stabilize soft agricultural land for crane use, completing winter installation on schedule in four weeks.
Resilient rural road construction in Thailand using MIRAFI H2Rx geotextile
A rural road in Thailand was upgraded using MIRAFI H2Rx geotextile to reinforce soft clay subgrade and manage high groundwater, ensuring durability, reduced moisture, and uninterrupted community access during construction.
Strengthening canal-adjacent road infrastructure in Thailand with MIRAFI H2Rx
MIRAFI H2Rx geotextile was installed over 27,000 m² to reinforce a road near Maharahj canal, improving pavement strength and moisture control while preventing embankment failure and completing 3 km in just 5 days.