Extending parking lot overlay life at Hillsborough College – Brandon Campus
Hillsborough College – Brandon Campus used Petromat® MPV500 paving fabric to improve bonding, delay reflective cracking, and support longer-lasting pavement rehabilitation.
The Naval Base Point Loma planned to construct eight fuel storage tanks on soft soil foundations. The design for these large-diameter tanks included stone column footings. To ensure safety in case of a fuel spill, cast-in-place containment dike walls were built around the tank farm. During the excavation of the dike wall footings, the contractor encountered soft pumping subgrade. Solmax was then consulted to provide a solution for stabilizing the subgrade. This modernization effort was crucial for maintaining the operational readiness of the U.S. Navy and other agencies that rely on DFSP Point Loma, including the U.S. Marine Corps Air Station Miramar and the U.S. Coast Guard.
To address the subgrade stabilization at the Naval Base Point Loma, MIRAFI® RS580i geotextile was placed directly on the soft pumping subgrade. This was followed by a 12-inch (30 cm) layer of 2-inch (5 cm) diameter crushed stone, which was spread using bulldozers and then compacted. Above this stone layer, a MIRAGRID 2XT biaxial geogrid was installed. An 8-inch (20 cm) section of crushed recycled concrete was then placed on the geogrid. Water was added to this crushed base material, and the entire section was compacted to create a tight foundation ready for the dike wall concrete footing.
This method ensured a stable and secure foundation for the containment dike walls, addressing the challenges posed by the soft subgrade and enhancing the overall safety and integrity of the fuel storage facility.
To address the subgrade stabilization at the Naval Base Point Loma, MIRAFI RS580i geotextile was utilized to eliminate the pumping subgrade condition. This high-performance geotextile provided superior tensile strength for subgrade support and effectively separated the pumping soils from the aggregate base. Additionally, it offered filtration and drainage of water from the pumping soils, as well as lateral confinement of the stone section. This stabilization method ensured a secure platform for the construction of the cast-in-place fuel containment dike walls, enhancing the overall safety and integrity of the fuel storage facility.
A layer of MIRAGRID 2XT biaxial geogrid was installed above the crushed stone
Water was added to the crushed base material before compaction, creating a tightly bound foundation section suitable for supporting the dyke wall concrete footing
The installation of MIRAFI RS580i provided tensile strength, separation, filtration, drainage, and lateral confinement, resulting in a stable platform for constructing the fuel containment dyke walls
Extending parking lot overlay life at Hillsborough College – Brandon Campus
Hillsborough College – Brandon Campus used Petromat® MPV500 paving fabric to improve bonding, delay reflective cracking, and support longer-lasting pavement rehabilitation.
Managing differential settlement on soft landfill soils with MIRAFI
MIRAFI® RS380i stabilized pavements at FLETC Charleston over soft marine clays and landfill soils, reducing settlement risk while improving constructability and lowering costs.
Geosynthetic reinforcement enables vertical landfill expansion on soft soils
Cherry Island Landfill needed more disposal capacity on a constrained site underlain by weak, compressible soils. Solmax geosynthetic reinforcement helped make vertical expansion possible and delivered more than 20 years of additional disposal life.