Biosolid removal with GEOTUBE dewatering units
Desilting Solutions removed 150,000 m³ of biosolids from sludge lagoons at three operational sewerage treatment plants using GEOTUBE dewatering containers for efficient dewatering.
Continuous rainfall caused a major landslide on the Federal Route leading to Langkawi's highest mountain (881m/2,890 ft). This area houses a museum, a park, and a satellite control centre. The landslide severely disrupted traffic and posed risks to road users.
The high, steep, and unstable failed slope made it difficult to trim it into a gentler gradient using conventional methods. After considering various solutions, PWD engineers decided to realign the road, moving it 30m (98 ft) away from the failed slope. This required constructing a geosynthetics reinforced slope starting from the toe of the failed area below the road.
Since there was no granular material available at the site, the design focused on using the fine sandy soil already present as backfill. MIRAFI® Polyfelt PEC reinforcement geotextile was chosen due to its high tensile strength, optimal reinforcement/soil friction interface, and effective in-plane drainage in such soils.
The reinforced soil structure consisted of a 30m-high (98 ft) slope reinforced from the toe of the failed embankment. The facing system used involved wrapping a net around bags filled with fine-grained soil. This construction method allowed for the practical creation of a curved slope. MIRAFI Polyfelt PEC was placed behind the gabion and soil bags to enhance the structure's strength. Additionally, a layer of MIRAFI Polyfelt PEC TS geotextile filter was installed behind the gabions to prevent soil piping through the voids.
The primary reinforcement direction of MIRAFI Polyfelt PEC was perpendicular to the slope's surface. The reinforcement geotextile was pretensioned and secured with wooden pegs. Backfill material was compacted using a 10-ton compactor to achieve a minimum of 90% proctor compaction. Finally, hydroseeding was performed to establish vegetation on the completed slope.
Slope failure repair using MIRAFI Polyfelt PEC: Langkawi, Malaysia
Slope failure repair using MIRAFI Polyfelt PEC: Langkawi, Malaysia
Biosolid removal with GEOTUBE dewatering units
Desilting Solutions removed 150,000 m³ of biosolids from sludge lagoons at three operational sewerage treatment plants using GEOTUBE dewatering containers for efficient dewatering.
Creating a recreational pond with GSE geomembrane at Kiki Beach Resort
Kiki Beach Resort on Batam Island installed GSE HD 1.50 mm White Smooth for a recreational pond to enhance visual appeal and durability. The solution included custom roll sizes and a GSE Polylock anchoring system to meet design and site challenges.
Restoration of submerged stormwater pipeline
Desilting Solutions restored a submerged stormwater pipeline in Milton, Queensland, to 97% capacity using GEOTUBE technology and remote dredging within a confined site.