Rebuilding resilience: post-wildfire erosion control on Pacific Palisades bluff
A homeowner used PROPEX Armormax to protect a bluff damaged by the Pacific Palisades fire to reduce erosion risk, support revegetation and mitigate future wildfires.

Murrieta Creek has a history of devastating flooding. Notably, the flood of 1993 that claimed the lives of five people and damaged 70 aircraft and two bridges at Pendleton Marine Corps Base. The flood also inundated pumps at the Eastern Municipal Water District, causing 5 million gallons of raw sewage to flow into the creek. Multiple major flood events have occurred since the 1993 flood. Today, more than 600 homes and commercial structures are vulnerable to flooding.
In 2000, the U.S. Army Corps of Engineers initiated the Murrieta Creek Flood Control, Environmental Restoration and Recreation Project to mitigate flooding. In phase two of the project, PROPEX® Armormax was selected to provide erosion and scour protection on the creek banks.
The system consists of High Performance Turf Reinforcement Mat (HPTRM) and earth anchors that provide resilient flood control for up to 75 years. Maintaining water quality was a main concern because Murrieta Creek is recognized as one of the last high quality, minimally disturbed riverine environments in Southern California.
PROPEX Armormax helps to decrease sedimentation and pollutants and encourages infiltration of water back into the groundwater table. The system also promotes rapid root development for long-term vegetation, whereas rock riprap, can decrease streamside vegetation and adversely impact fish populations. Vegetation was quickly established, and PROPEX Armormax has effectively protected the channel from erosion and flooding





Rebuilding resilience: post-wildfire erosion control on Pacific Palisades bluff
A homeowner used PROPEX Armormax to protect a bluff damaged by the Pacific Palisades fire to reduce erosion risk, support revegetation and mitigate future wildfires.
Seawall construction, Brisbane Port expansion, QLD, Australia
The Port of Brisbane expanded by constructing a reinforced seawall to enable 230 ha of land reclamation using dredged materials while managing soft clay foundations and protecting the Moreton Bay Marine Park.
High speed railway embankment over karst foundation, Guizhou Province, China
The Anshun–Liupanshui high-speed railway crosses challenging karst terrain in Guizhou Province. Two layers of MIRAFI PET600 geotextile reinforcement were installed at the embankment base to limit deformation and manage subsidence risk under strict settlement criteria.