Shute Harbor, an important gateway to Whitsunday Island hotels and the Great Barrier Reef, was severely damaged by Cyclone Debbie in March 2017. As part of the reconstruction efforts, the seawall and jetties required a major redesign and reconstruction.
In a groundbreaking application for Australia, customized panels of MIRAFI® PET2000/100 geotextiles were used as reinforcement under a rock amour revetment. These panels were designed to accommodate differential revetment subgrade settlements and withstand hydraulic and storm surge demands.
Design considerations:
The design called for specially fabricated geotextile panels that were securely connected to each other. The panels needed to be installed along the revetment and seabed without exerting lateral pressure on the supporting piles. Additionally, the panels had to adapt to varied soil conditions and meet specified connection strengths.
The construction process:
To meet these requirements, Solmax supplied specially fabricated MIRAFI PET 2000/100 kN/m (450 lb/ft) panels. Each panel was custom-made in length and profile to ensure that the fabric remained under tension without affecting the piles. The panels were designed with an innovative interconnected loop system, allowing positive connections both above and below water. Extensive dialogue with the contractor and consulting engineer, along with pre-delivery testing, ensured that the proposed solutions met the technical requirements and installation plan.
Panel delivery and installation:
Each panel was delivered according to the laydown design schedule, with careful sequencing to match the installation sequence. This approach ensured smooth installation, starting with the first panel unloaded on site. Despite encounters with a saltwater crocodile and a hammerhead shark, the installation of MIRAFI PET 2000/100 geotextiles proceeded as planned and was successfully completed.

SHUTE HARBOR, QUEENSLAND, AUSTRALIA 1

SHUTE HARBOR, QUEENSLAND, AUSTRALIA

SHUTE HARBOR, QUEENSLAND, AUSTRALIA
Rebuilding resilience: post-wildfire erosion control on Pacific Palisades bluff
A homeowner used PROPEX Armormax to protect a bluff damaged by the Pacific Palisades fire to reduce erosion risk, support revegetation and mitigate future wildfires.
Seawall construction, Brisbane Port expansion, QLD, Australia
The Port of Brisbane expanded by constructing a reinforced seawall to enable 230 ha of land reclamation using dredged materials while managing soft clay foundations and protecting the Moreton Bay Marine Park.
High speed railway embankment over karst foundation, Guizhou Province, China
The Anshun–Liupanshui high-speed railway crosses challenging karst terrain in Guizhou Province. Two layers of MIRAFI PET600 geotextile reinforcement were installed at the embankment base to limit deformation and manage subsidence risk under strict settlement criteria.